We’re currently installing larger, more resilient wastewater pipes under Stage Highway 59, near Mepham Place. To achieve this, we are using a technique called pipe ramming. By drilling a hole into the ground and pushing the pipes through, it means we can install the new, steel wastewater pipes more faster and efficiently.
It’s important to note that whilst this technique is quicker, safer and cheaper, this technique does create loud banging noises, followed by vibration. Our team are mindful of the impact this will have on residents, so are working as quickly as they can to ensure any loud noise or vibration is kept as short as possible.
Project update (as at 2 December 2024)
From mid-October, our contractors are installing six cases (or pipes). They have moved on to installing the last casing, which means we’re on track to completing the pipe ramming work by mid-December.
Planning your day
Below is our current work schedule for pipe ramming. We do suggest, if you are able, to take regular breaks from the area.
Day |
Date |
Activity |
Weather |
Tuesday |
26-Nov |
Remove soil from casing |
Fine |
Wednesday |
27-Nov |
Remove soil from casing & set up hammer gears |
Fine, then a few showers in the evening |
Thursday |
28-Nov |
Ramming casing (7:30am-6pm) |
Fine |
Friday |
29-Nov |
Ramming casing if needed/weld casing |
Fine, then a few showers in the afternoon |
Saturday |
30-Nov |
Weld casing |
Fine |
Sunday |
1-Dec |
No work |
Fine |
Monday |
2-Dec |
Welding casing & removing soil |
A few showers |
Tuesday |
3-Dec |
Remove soil & set up gears - possible ramming casing |
A few showers |
Wednesday |
4-Dec |
Ramming 6th casing |
A few showers |
Thursday |
5-Dec |
Ramming 6th casing if we’re unable to finish on Wednesday |
Fine |
Friday |
6-Dec |
Soil removal | Fine |
Saturday |
7th Dec |
Soil removal |
Fine |
Stay up to date
Whilst we update this webpage frequently, we are also sending emails to neighbours to help them up to date with work progress and any changes to the schedule.